What
steps are involved in the building process?
online signature loans
The
steps to a completed building vary from church to church but generally
all of the building process steps should be taken in order to avoid
costly and untimely mistakes. The initial studies and the budget are
very important initially. You should be aware of what the suggested
steps are and how long you might expect all of this to take.
-
Conceptual
planning/feasibility studies: 6-12 weeks
-
Preliminary
design 6-12 weeks
-
Working
drawings 12-16 weeks
-
Bidding
and contractor selection 3-6 weeks
-
Securing
financing 3-4 weeks
-
Permitting
3-8 weeks
-
Construction
6-18 months