Ten Mistakes To Avoid
Before You Build
|
| |
|
работа моделью.
Before
your church gets involved in a building project, make sure you
count the cost.
By
Jeff Dunn
The decision to expand St. James United Methodist Churchs
building was an easy one to make.
We knew it was time to expand, says Jeffrey Johnson,
associate pastor of the Tulsa, Oklahoma, church, when we
couldnt squeeze one more child in a Sunday school classroom.
For others the decision to build is not as clear. South Dayton
(Ohio) Presbyterian leased an auditorium from a local Seventh-day
Adventist school for 6-1/2 years before breaking ground for their
own complex. We could have waited another year to collect
more funds, reflects Don Ward, pastor of South Dayton Presbyterian.
Both Johnson and Ward confess to making mistakes during the planning
and building process. These pastors, along with several construction
and financial planning experts, talked with MINISTRIES
TODAY about what to do and what not to do when launching a
church building project.
Here are 10 mistakes often made by ministers in building or expanding
their churches. We hope you can avoid the same pitfalls.
| |
Mistake
#1. Failure to conduct a needs analysis.
|
Yes, you realize you need more space. But what
kind of space do you need? Can existing space be utilized,
or will you have to add to your building? Do you have
the land to expand?
These questions and others should be answered during
a needs analysis or feasibility study. Such a study
should be done by an architect before any other phase-
even before the selection of an architect to design
your plans.
Having an unbiased, outside source do a feasibility
study allows a better view of the churchs needs,
says Larry Barnhill, vice president of A-E
Technologies. Once a congregation gets
beyond their emotions and feelings, they can see the
facts. Otherwise, you can end up with a church designed
by a committee.
Barnhill, vice president of operations for the 10-year-old
company, cautions pastors not to confuse planning
with plans.
Planning, he explains, is taking
us from where we are to where we want to be. A plan-
the drawing of a building- is where many architects
want to start. The architect asks, What do you
want to build? What most churches need is someone
to ask, What do you need- and why?
Dont think of building what you need now,
says Johnson. Plan to build what you will need
five years from now. Johnson explains that shortly
after the first phase of St. James building
was finished in 1988, they were already overcrowded
in classroom space. Wise use of space above several
rooms allowed for a temporary solution until the second
phase could begin in 1996.
Build a building that can be added onto,
says Johnson. Start from the end- what you want
it all to look like- and work back. Picture what the
whole campus should look like after all the phases
are completed.
Churches are the biggest tearer-uppers
of asphalt in the country, according to Brachial.
They tear up a parking lot to add to the building
when they shouldnt have put the parking lot
there in the first place. You should plan your building
for future growth.
A healthy church will grow, says Johnson
enthusiastically. Build your church to accommodate
growth.
|
|
| |
Mistake
#2. Selecting the wrong architect or builder.
|
Barnhill believes it is imperative to choose a Christian
architect.
His Christian perspective allows him to ask
the right questions, Barnhill says, and
allows him to understand the use of your building.
After all, a building is a tool for use in your ministry.
Ward chose a Christian builder and trusted that as
a Christian he would do everything in an upright manner.
Now he wishes he had not been so trusting. The contractor
was using money given him by Wards church to
pay subcontractors on other jobs. Money soon ran out
for Wards project.
If he had been a secular contractor, says
Ward, we would have held his feet to the fire.
Now I know that just because a worker is Christian
doesnt mean we should fail to hold him accountable.
Set up procedures and then stick to them. Dont
take excuses.
Ward admits he did not check the builders references
closely enough. He suggests checking the two or three
most recent projects completed by the builder rather
than ones done several years ago.
If he has any history of late payments,
warns Ward, you dont want anything to
do with him, whether he is the lowest bidder or not.
|
|
| |
Mistake
#3. Relying on the architects cost estimate.
|
Scott Rolfs, assistant vice president with B.
C. Ziegler and Co., a firm specializing in church
financing of large-dollar ($1 million or more) projects,
sees this problem arise constantly.
We look at any number of multi-million dollar
projects every week, he says. The architect
tells the church it is a $1.2 million to $1.5 million
project; then the bids come back from the builders
10 to 20 percent higher. The problem is the pastor
has sold the congregation on the architects
price. The congregation gets sticker shock
when they are told what it will really cost to build.
Then there are the costs not written into the original
plans that can end up adding tens of thousands of
dollars to the project- or shutting it down completely.
Things not foreseen by the architect, such as street
improvements or the addition of a traffic light, can
drastically increase the overall cost.
Who is going to pay for the building redesign
if it comes in over budget? asks Barnhill. The
architect should be willing to redesign at no cost,
even if that means starting over. Thats our
policy- its a matter of integrity. If the bid
exceeds the projected cost by 7 percent, well
redesign at no cost to the church.
|
|
| |
Mistake
#4. Improper site selection.
|
Proper site selection is the key, says Ward. It
makes all the difference, he insists. We
chose a site on a high-traffic road. We get a lot
of visitors just from drive-bys.
But it is a much more difficult chore than it was
a decade or so ago.
Gone are the days when you could just go out,
buy a plot of land and build a church on it,
says Barnhill. Now there are numerous environmental
issues to investigate.
Barnhill and Rolfs both stress the importance of the
completion of an environmental study before bidding
on property. Its the best insurance you
can buy, insists Rolfs. Its comparable
to having a home inspection before buying a residence.
The Phase One environmental study tells if there are
contaminants on the property. The owner is responsible
for the proper removal of these contaminants, whether
or not he is the originator of the hazard. And the
removal of these wastes can be very costly.
The cost of the Phase One study, according to Rolfs,
ranges from $500 to $3,000. Sometimes you can
get the seller to pay, he says. Barnhill suggests
you check with local planning commissions to see exactly
what environmental studies should be undertaken before
deciding on a piece of land.
|
|
| |
Mistake
#5. Failure to plan for adequate parking.
| |
This is one area many church planners overlook,
to their detriment. Barnhill says, There is
no use building a 1,000 seat sanctuary if you can
park only 500.
Leave room for growth, is the advice of
Rolfs. If your lot is full, visitors wont
stop. Ward knows this to be true. They have
been in their new building for only two years, and
already their parking is overflowing.
We have 20 cars a week parking across the street,
says Ward. On Easter Sunday it was more than
40.
Most city zoning codes call for a ratio of 1 car to
every 4 seats when it comes to planning parking. But
both Ward and Barnhill believe a more realistic ratio
is 1-to-2 or 1-to-2.5. Its a mistake to
apply code requirements that are too low, says
Barnhill.
|
|
| |
Mistake
#6. Unrealistic projection of income or inadequate cash
on hand.
|
This sixth mistake can easily outweigh all the others
up to this point. You can have great planning, great
drawings, a beautiful and environmentally friendly
site, and room for all the cars General Motors will
make in a year. Yet without proper financing, all
your plans will lie in a drawer gathering dust.
"Most churches start by talking about their needs,
states Barnhill. They should start by talking
about their financial capabilities. Based on the size
of the church, how much money can they realistically
raise and borrow?
In the lending business, says Rolfs, we
frequently get calls from churches who are putting
up a $2 million project. They have members who have
pledged $1 million over the next three years, so they
believe they need to borrow only $1 million.
But they dont realize that contractors
must be paid while the building is going up, not three
years from now. They must pay the interest on the
loan. Plus unexpected costs must be added in. Then
take into account that, historically, pledge collectability
is only around 70 to 80 percent. The church has to
be realistic about what it needs to borrow to finance
the project.
Ward experienced this scenario firsthand. When
we moved into the new building, he recalls,
we had a huge mortgage to pay, but hadnt
yet grown to where we could pay it.
And there is the catch: A church cant grow in
an outgrown or outdated building, but while it is
still small, it cant afford to build a larger
building to accommodate new growth.
Heres how we suggest churches handle that
dilemma, says Barnhill. We encourage churches
to start a capital funding campaign. They should conservatively
be able to raise one to 1-1/2 times their annual giving.
This is usually enough to make up the shortfall in
monthly expenses with the new mortgage until church
growth catches up with the need. You should have a
36-month cash-flow bridge while the church
is growing.
Rolfs also encourages churches to be realistic about
the sale of their existing site. Church properties
dont turn quickly, he says. The
normal marketing time for church property is eight
to 30 months. And, if you are in a smaller town, your
prospects are limited.
|
|
| |
Mistake
#7. Getting on the bad side of city government.
|
According to Barnhill, zoning issues for churches
are getting more and more testy.
I think its Satans last attempt
to retard the growth of the church, he says.
Says Johnson, You never want to make the city
your enemy.
Weve taken huge shots from the city. Fifty
thousand dollars to install storm water management
when we first built, another $75,000 during our second
phase to correct it. They said it wasnt up to
specs- but it was their specs we followed in the first
place!
Ward concurs, Weve had mega-problems with
the city. They are extremely inflexible and legalistic.
It would seem that friends like these
could easily become your enemies.
Be sure your testimony extends to the city,
exhorts Johnson. Were here to minister
to the city. We pray for the city officials.
This is one area we did right, exclaims
Ward. We responded to objections raised at the
zoning board hearing. There were concerns raised about
drainage, so we made improvements to the plans that
helped the situation in the whole neighborhood. We
didnt have to do that, but it created a win-win
situation. And if the city leaders want to take all
the credit, let them!
|
|
| |
Mistake
#8. Allowing the project to overwhelm your life.
|
The very week Don Ward was to witness the dedication
of his new church building to the service of the Lord,
he almost left the church.
I got too emotionally involved, he says.
I felt I was carrying it all on my back. As
a result, my wife and I felt burned out. I had a job
offer the week before our dedication service.
He turned it down and is glad today he did.
It would have been a mistake, he admits.
We have had dramatic growth since the dedication.
I just didnt have a good infrastructure under
me in the church. Now we are talking expansion again,
but I wont make the same mistake. Ive
told the church, If you want to build, you do
the work. Im not even going to all the
meetings.
|
|
| |
Mistake
#9. Not praying for the construction workers.
|
How easy it is for us to miss opportunities to see
God work right in front of us each day! Johnson was
able to see Gods faithfulness in answering prayer
as the first phase of St. James was being built in
1988.
We prayed for the safety of the workers everyday,
says Johnson. One afternoon a carpenter put
his foot through the roof and fell what would have
been about 40 feet. He reached out and grabbed a beam
in the sanctuary. One of our members walked in right
then and was able to get him down. What a miracle
from our Lord! And that worker was in church the next
Sunday.
Perhaps not the ideal church growth method, but if
it works
|
|
| |
Mistake
#10. Waiting to celebrate until the building is complete.
|
Johnson tells how his church celebrates the
completion of various steps. For instance, when they
had completed their fund-raiser for the second construction
phase, the church hosted a catered dinner at a nice
restaurant for all the adults in the congregation.
They held an Enlarge the Harvest
concert one Friday night just to gather the members
in an attitude of praise to God for His faithfulness
thus far in the project.
And celebrate big when you finish, suggests
Johnson. Be sure to recognize all those who
helped make it possible.
JEFF DUNN is a free-lance writer living in Dayton,
Ohio.
Reprinted with permission from MINISTRIES
TODAY.
|
|
|